Onslow Ramp Takes About Two Years From Shovel

Normal mining projects take four to seven years from construction start, but Mineral Resources had approvals in under a year and expects Onslow to reach nameplate capacity about two years after breaking ground.

factualpending

Speaker

Fraser

Evidence Quote

“So let's call it two years from shovel hitting to nameplate capacity.”

Source

Mineral Resources: Unearthing Value— Business Breakdowns