Four Nines Uptime Requires 2.5x Solar Overbuild
To achieve four nines of uptime for AI data centers you need solar overbuild of about 2.5x: in Texas a 1 MW average load needs ~4 MW of panels (25% capacity factor) plus 2.5x overbuild yielding ~10 acres of solar, ~24 hours of battery (six Tesla Megapacks), with the overbuilt power 99.9% of the time exceeding need—which can then be sold to local utilities at near-zero marginal cost, inverting the data-center-must-curtail relationship.
factualpending
Speaker
Casey HandmerEvidence Quote
“So 10 acres of solar, six truckloads of batteries, one truckload of data center, and some cooling stuff.”
Source
China is killing the US on energy. Does that mean they’ll win AGI? — Casey Handmer— Dwarkesh Patel PodcastCreated: 6/13/2026, 3:25:18 AM