All of Black Rock's Tonopa operations sit on patented mining claims (private land), eliminating federal government involvement in permitting; after baseline surveys and engineering design, Nevada state permitting takes only 12-14 months (vs. 5-10 years for BLM/federal land).
factualpending
Speaker
Andrew PaardEvidence Quote
“private land in Nevada which our entire operation is situated on means that there's no federal government involvement in our permitting process whatsoever”
Source
Larry McDonald on Platinum, Palladium, Natural Gas + Altamira Gold & BlackRock Silver CEO Interviews— Resource TalksCreated: 8/11/2026, 12:29:49 AM